P384 Review

Lead Monitor Guidelines

 

Prior to the review

Day of the review

Following the review

60 � 45 days

45 � 30 days

14 � 7 days

30 � 60 days

v      Contact agency

       notify of review date -or- negotiate alternate date

 

v      Contact IPI

       coordinate with Medicaid review

 

v      Contact Licensing

       coordinate with annual review

 

v      Select team members with RPM Mgr.

 

 

v      Send letter to agency

       see form letter

       confirm review date

       request QA information

 

v      Select, notify peer

       agency chooses 3 from peer list

       monitor, RPM Mgr pick 1 of 3

       if no peer response in 3 days, select another

 

v      Notify team members

       date/time of review, assignments

       notify RPM Mgr. if member unavailable

v      QA Mgr receives QA information from agency

 

v      Clarify expectations with agency

       adequate space for file reviews

       agency coverage for staff during interviews

       private space for interviews

 

v      Email reminder to team

       give review date, time, directions, other relevant information

 

v      Obtain UIR information from QA

 

v      Select youth for review

       15% of all youth, or minimum of 4

 

v      Develop schedule for day of review

 

v      Copy documents for team members for day of review

       P384

       P384 file review tool

       P384 questionnaires for clients, direct service staff

v      Finalize review day schedule

       identify scheduled staff for interviews

       notify agency of youth for review (NOTE: no youth to be removed from school)

 

v      Facilitate introductory meeting

       keep it brief!

       introduce participants

       distribute review schedule

       answer agency questions

 

v      Receive file orientation

       keep it brief!

 

v      Receive facility tour

       keep it brief!

 

v      Complete file reviews/interviews

 

v      Process preliminary findings with team members

 

v      Present preliminary findings to agency administration

       Lead Monitor, RPM Mgr., QA Mgr. only

 

 

 

v      Complete draft review report with recommendations

       send draft interview section to interviewers (give 1 week for feedback)

       send draft file review section to file reviewers (give 1 week for feedback)

       send draft report to L. Karfs by 30th day after review

 

v      QA completes draft QA portion of review report with recommendations

 

v      Review draft reports with L. Karfs, QA Mgr.

 

v      Consolidate QA portion into overall report

 

v      L. Karfs approves, forwards completed P384 report to N. Brown and agency

 

 

 

*